PRACTICAL GUIDE

How to assess a contractor PQQ and supporting evidence

A proportionate approach to contractor pre-qualification questionnaires, evidence gaps and recorded decisions, with a fictional construction example.

By The Logic Suite · Published 12 October 2026 · Sources checked 12 October 2026

Founder: Lloyd Godsall — qualifications and experience. These guides use official sources and illustrative examples; they are not accounts of completed pilot projects.

Construction work area with groundworks
Site photography by Lloyd Godsall. Photograph illustrates construction context, not the fictional example.

A pre-qualification questionnaire, or PQQ, helps collect information about a prospective contractor. The assessment should explain whether that evidence is relevant to the proposed work and what still needs checking. A completed questionnaire alone does not establish that the contractor can deliver every activity safely.

Define the package before asking for evidence

Describe the work, location, anticipated hazards, interfaces and supervision expectations. Ask questions that help assess that package. Avoid treating a large collection of unrelated certificates as a substitute for understanding who will do the work and how it will be managed.

HSE’s Using contractors explains the wider process of selection, risk assessment, information, cooperation and supervision. For construction, also see HSE’s guidance on appointments and capability.

Connect each answer to evidence

Record the evidence reference and what it supports. A company policy describes an arrangement; it does not by itself show how the arrangement is used on the proposed job.

A worked example of an evidence gap

Fictional learning example. This is an assessment approach, not a certification scheme or approval of a real contractor.

A contractor applies for an internal refurbishment package. Its response includes examples of similar work and a training list, but the proposed supervisor is not identified and the submission does not explain coordination with occupants.

QuestionEvidence receivedAssessment and next step
Relevant experienceTwo similar project summaries.Discuss the contractor’s role and the interfaces on those jobs.
SupervisionGeneral training list.Request the proposed supervisor and relevant experience. Record a named assessor and response date.
Occupied building arrangementsNo package-specific explanation.Clarify coordination, communication and proposed management arrangements before deciding suitability.

Record a decision that someone can understand

The assessor records “further information required” and lists the unresolved supervision and occupancy questions. The follow-up has an owner and due date. Once the response arrives, the assessor records what changed and why it affects the decision.

Use your organisation’s decision criteria. If conditions are attached to an appointment, make their scope, owners and deadlines explicit. Do not describe a contractor as approved for all work when only a particular package has been considered.

Continue the checks after selection

Confirm that the people and arrangements proposed are the ones used. Share relevant site information and coordinate interfaces. Monitor performance and respond to changes. Pre-qualification belongs within contractor management, rather than being its final step.

Where Contractorlogic fits